Axe Compute Revenue Jumps 125 Percent to $7.2 Million
Axe Compute reported third quarter 2026 revenue of $7.2 million on November 17, 2026, up 125 percent from $3.2 million in the second quarter. Net income was $11.5 million, and the company holds signed contracts worth more than $3 billion that haven't produced recognized revenue yet.
Edited and fact-checked by Stephen Sprague
The Georgia cluster goes into service first. Customer acceptance is under way, the first Build deployments are targeted for the fourth quarter, and Build revenue starts only when those clusters deploy.
In Miami on Tuesday, a company that sold its cancer business in September reported GPU numbers instead.
Axe Compute posted third quarter revenue of $7.2 million, up 125 percent from $3.2 million in the second quarter. It's the second straight quarter of triple-digit sequential growth. Every dollar came from the Access model, the company's rental-style GPU service under fixed-term contracts.
The profit line needs its footnote read out loud. Net income was $11.5 million, or $0.52 a share diluted, against a $17.2 million loss in the second quarter. The release counts $15.0 million of gains inside that result, mostly non-cash fair value changes on digital assets and on the securities it took for Helomics. Adjusted EBITDA was about negative $2.3 million.
Customers are funding the buildout before it exists. Cash grew to $147.7 million at September 30, and contract liabilities, which are customer prepayments, jumped to $569.3 million from $60.8 million at June 30. The company spent $349.6 million on GPU infrastructure in the quarter, and construction in progress stood at $366.7 million.
Georgia holds the first hardware the company actually owns. On September 30 it acquired a cluster of 2,304 NVIDIA B300 GPUs, arranged as 288 Supermicro NVL8 servers, for $124.4 million. The cluster sits in a Duos-operated data center with about 5 megawatts of committed power. It's energized and provisioned, customer acceptance is under way, and the customer contract now runs five years, through 2031.
The signed paper is much larger than the recognized revenue. Three Build contracts signed in July across the United States and Europe carry more than $2.8 billion in total contract value, and the company puts its 2026 total above $3 billion. It expects more than $700 million in annualized run rate once everything deploys. None of that Build money is in the $7.2 million. Recognition starts at deployment, and the first Build cluster is targeted for the fourth quarter.
Helomics closed the old company's last chapter. Axe sold the oncology subsidiary on September 11 for 636,328 shares of DataMeds common stock and a $1.4 million convertible note. In November the headquarters moved to 801 Brickell Avenue in Miami. What's left is a single segment, GPU compute, and a delivery schedule it now has to meet.