Bimergen Posts First Revenue From Battery Storage Projects
Bimergen Energy reported third quarter 2026 results on November 17, 2026. Revenue was $3.0 million against none a year earlier, net income was $2.4 million, and the quarter's money came from transactions on three Texas battery storage projects totaling 480 megawatt-hours, not from operating plants.
Edited and fact-checked by Stephen Sprague
The pipeline is the next measurement. Bimergen lists about 2.0 gigawatts across 33 projects, and its own release warns that quarterly revenue will vary with the timing of project transactions.
In Newport Beach on Tuesday, Bimergen reported revenue where a year ago it reported none.
Third quarter revenue reached $3.0 million, compared with no revenue in the same quarter of 2025. Gross profit was $0.7 million. Net income was $2.4 million, or $0.33 a share, a $4.2 million improvement from the $1.8 million loss a year earlier and a 50 percent rise from the second quarter's $1.6 million.
The source of the money matters more than the total. During 2026 the company completed transactions on three battery storage projects in Texas's ERCOT market, with 480 megawatt-hours of planned capacity combined. Those development deals produced the revenue. Bimergen kept a 7.5 percent equity interest in the projects, and it describes the model plainly. It develops battery farms, brings in institutional capital partners and books revenue at development milestones.
That distinction sets the evidence boundary for the quarter. A megawatt-hour sold in a development transaction isn't a megawatt-hour dispatched to the grid. The release says operating revenue arrives later, once projects are built and can buy power at lower prices and sell it back at higher prices. None of the three Texas projects is described as operating in this report.
The balance sheet moved with the deals. Cash was $7.8 million at September 30. Working capital was $8.8 million, against a deficit of $4.5 million at December 31, 2025, an improvement of $13.3 million. Total assets were $40.5 million and stockholders' equity was $36.1 million, with 7.4 million fully diluted shares. Adjusted EBITDA was $3.0 million, the second straight positive quarter.
Nine-month revenue totaled $10.9 million, all of it in the second and third quarters. Those two quarters produced $5.5 million of gross profit and $4.1 million of net income. The company uplisted to NYSE American in February 2026, and it presents 2026 as the year the development pipeline started converting into financial results.
The remaining pipeline is larger than the part that has paid. Bimergen lists about 2.0 gigawatts across 33 battery storage projects in the ERCOT, PJM, WECC and MISO markets. Its Redbird project near Houston carries planned capacity of 100 megawatts and 400 megawatt-hours. The release also states the limit on its own numbers. Quarterly revenue will vary with transaction timing, and steady revenue is an expectation for coming years, not a result in this quarter.