Keel Sells Entire Bitcoin Treasury In Data Center Pivot
The former Bitfarms sold 2,520 bitcoin for $192 million, ended its U.S. mining business and now runs on about $780 million of cash while it builds data centers.
The treasury is empty, and that is the strategy.
Keel Infrastructure sold its entire bitcoin treasury in the third quarter, 2,520 coins for $192 million, and holds no bitcoin exposure on purpose.
The quarter's numbers split into two piles. Revenue from continuing legacy operations fell to $28 million from $68 million a year earlier, because the company stopped mining bitcoin in the United States during the second quarter to build data centers instead, and the average bitcoin price fell with it. The loss from continuing operations widened to $62 million, or $0.10 a share, from $11 million, or $0.02 a share. A $55 million non-cash paper loss on capped calls tied to the company's 2025 convertible notes did most of that widening. The operating loss narrowed to $8 million from $18 million, and adjusted EBITDA swung to negative $27 million from positive $19 million.
The treasury sale emptied the vault in one quarter. Keel sold 2,261 bitcoin it held in reserve plus the 259 it mined during the quarter, taking $192 million in proceeds at prices the company describes as periods of strength. Holdings stood at nominal levels on September 30. Bitcoin mined at the remaining Quebec operations now sells the day it's mined, so the treasury no longer rides the coin's price in either direction.
Spending moved the other way. General and administrative costs doubled to $34 million from $17 million, on senior hires, professional fees and higher stock-based pay as the company staffs a project management business. Against that burn sits about $780 million of unrestricted cash, counted on November 4. "We remain strongly capitalized, with approximately $780 million of cash liquidity and no current need for debt or equity financing before signing a lease," said Jonathan Mir, the chief financial officer. "Capital we deploy ahead of a lease becomes part of our equity contribution to a project's financing."
For businesses
Amazon Business is Amazon’s purchasing store for companies, with business accounts and quantity ordering.Register with Amazon BusinessConstruction started at Moses Lake in September, after the last permit cleared, and the site should be the first one energized, with high-performance computing revenue expected in 2027. The company engineered an optional layout there for Nvidia's next Vera Rubin architecture. Permitting advanced at the Sharon and Panther Creek sites in Pennsylvania, where revised plans meet the state's new executive order without meaningful changes to cost or timing. Load studies at Panther Creek and Scrubgrass could lift the company's secured data center capacity from 478 megawatts to 1,928 megawatts, with results due in the first quarter of 2027.
"Power supply is getting scarcer while demand keeps climbing," said Ben Gagnon, the chief executive. "Keel's 2027 and 2028 power is further advanced, more secure, and closer to delivery than it was last quarter." Lease negotiations are running at all three near-term sites, with several creditworthy parties at the table, and Gagnon said the company expects to sign the leases that return the most to shareholders.
No lease has been signed yet. Until one is, Keel is a $780 million cash balance, a construction site in Washington, permitted land in Pennsylvania and a mining past it sells off one day at a time. The first data center revenue is a 2027 event, and the cash has to last until the tenants arrive.